Building Painting Project Update from 12-23-2020 (pdf)
DownloadWindow replacements at Rio Del Sol require the pre-approval of the Board of Directors. Requests must be submitted in writing and include the approved window as well as approved installer:
River Valley Window Company
928-505-8198
Approved Window: Milgard Bronze Aluminum frames with Suncoat Max Low-E Glass
1. Stucco and Paint Repairs Status:
Investigating stucco concerns and new products - obtaining bids
Product Testing to occur as soon as weather permits.
2. Plaster failure on spa closest to Clubhouse
Must be re-plastered - Big Blasters Hired & Deposit Paid.
3. Patio Chairs - 6 New Chairs arrived and removed from storage. Placed on property 10-12-2020.
Stained Chaise Lounge - Restrapped on 12-28-2020
4. All Landscape Improvements On Hold until Building Painting is Completed
5. Several buildings have no antenna service. Sound Bank recommends installing an additional antenna on each building - waiting for quote as well as researching the best electrical option to provide power to the antennas (not every building has a common area power source)
REQUESTING VOLUNTEERS TO SERVE ON ANTENNA EXPANSION COMMITTEE
(Send Email to LHCfrontdesk@atmshoa.com if you are interested in joining)